What Is the LEAP District? Everything We Know (Updated November 2026)

Stefan Bean · November 15, 2026

Independent resource. Not affiliated with or endorsed by Eli Lilly, Meta, the LEAP District, or the State of Indiana. Sources linked.

  • leap district
  • lebanon indiana
  • boone county
  • lilly
  • meta
  • relocation
  • pillar

People ask me about LEAP almost every week, so here's the short version in one place. I'll keep this page updated as news comes out, and every fact links back to where it came from.

What LEAP is

LEAP stands for Limitless Exploration/Advanced Pace. It's an innovation district the Indiana Economic Development Corporation (IEDC) put together in and around Lebanon, in Boone County. The IEDC describes (opens in a new tab) it as 9,000+ acres on the I-65 corridor, about 30 miles from both Indianapolis and Purdue.

At full build, the IEDC says LEAP will be home to hundreds of companies employing over 50,000 people (opens in a new tab). That's a long-term goal, not a headcount you'll see this year.

Who's there today

Eli Lilly. Lilly is building three facilities at LEAP. The first one, Lilly Lebanon Advanced Therapies, opened May 6, 2026 (opens in a new tab). The Lebanon API site is expected to open in 2027 and the Lilly Medicine Foundry is scheduled for late 2027. Inside INdiana Business puts Lilly's total LEAP investment since 2022 at $18 billion.

Meta. Meta broke ground in February 2026 (opens in a new tab) on a data center campus representing an investment of more than $10 billion. Meta says it will support more than 4,000 construction jobs and 300 operational positions. The city's fact sheet (opens in a new tab) says the first buildings are expected to come online in late 2027.

What's proposed. In November the State Budget Committee took up a $20 million request to buy about 185 acres for a medical isotope project tied to Oklo. Lawmakers questioned the deal (opens in a new tab) because the land contract also lists nuclear power generation as a possible use. The committee approved the funding 4–1 on Nov. 10 (opens in a new tab). Nothing has been built, and a facility would still need local approvals.

The infrastructure behind it

Water. Citizens Energy Group has agreed to supply Lebanon Utilities with up to 2 million gallons a day by 2027 and up to 25 million by 2031 (opens in a new tab). The pipeline and booster work has drawn pushback in Hendricks County and around Eagle Creek. For treated wastewater, Lebanon Utilities is now looking at Prairie Creek (opens in a new tab) instead of Eagle Creek. A utility board vote is expected in January, with state approval to follow.

Roads. The new I-65/US 52 diverging diamond interchange near Lebanon opened in October (opens in a new tab), several months ahead of schedule. The State Road 32 realignment west of town is still under construction.

Housing and mixed use. In July the IEDC began seeking a master developer (opens in a new tab) for a roughly 1,000-acre mixed-use village inside LEAP. The plan includes housing, retail, dining and recreation north of SR 32 and west of I-65.

What's next on the calendar

  • 2027: Lilly Lebanon API and the Medicine Foundry are scheduled to open, and Meta's first buildings are expected online.
  • 2031: full water supply of up to 25 million gallons a day is planned.

You can see every dated milestone on our LEAP timeline.

Sources

  1. LEAP-Lebanon (opens in a new tab) · Indiana Economic Development Corporation · November 15, 2026
  2. Lilly announces additional $4.5B investment at LEAP District manufacturing site (opens in a new tab) · Inside INdiana Business · May 6, 2026
  3. Meta's New Data Center in Lebanon, Indiana Marks a Milestone AI Investment (opens in a new tab) · Meta Newsroom · February 11, 2026
  4. LEB Data Center Resources (fact sheet) (opens in a new tab) · City of Lebanon · June 2026
  5. Fight over water for LEAP spreads to Hendricks County (opens in a new tab) · WFYI / Free Press Indiana · October 8, 2026
  6. Troubled waters: Eagle Creek no longer an option for LEAP plan (opens in a new tab) · Current · November 8, 2026
  7. 52 at 65 Diverging Diamond Interchange Now Open Near Lebanon (opens in a new tab) · Boone County Daily News · October 5, 2026
  8. Proposals Sought for LEAP Mixed-Use Village (opens in a new tab) · City of Lebanon (IBJ content) · July 30, 2026
  9. LEAP District land purchase faces pushback over company's ties to nuclear power development (opens in a new tab) · Indiana Capital Chronicle · November 10, 2026
  10. Indiana Approves $20 Million for Oklo-Related Land at LEAP (opens in a new tab) · Lebanon, Indiana LEAP District (independent site) · November 11, 2026

All LEAP District news

Get LEAP updates

Leave your email to hear about sourced LEAP District updates.